Inspection Supply Chain Training CEO

IWCF Well Intervention Wireline Level 3 & 4

IWCF Well Intervention Wireline Level 3 & 4

مخطط الكورس

  • Application WL When wireline is used and the different types Available
  • Equipment WL Wireline equipment in different operating Environments
  • Surface PCE Stack WL CE required for wireline operations
  • Primary Barrier Elements WL Primary barrier elements used during wireline operations
  • Primary Barrier Elements WL Slickline primary barrier sealing elements and how to operate them correctly
  • Primary Barrier Elements WL Braided line/electric line primary barrier sealing elements and how to operate them correctly
  • Primary Barrier Elements WL Primary barrier element integrity during wireline operations
  • Secondary Barrier Elements – BOPs (Ram Type Preventers) WL Secondary barrier elements (wireline BOPs) used during wireline operations
  • Secondary Barrier Elements – BOPs (Ram Type Preventers) WL BOP ram configurations for different types of wireline
  • Secondary Barrier Elements – BOPs (Ram Type Preventers) WL How to operate secondary barrier elements (slickline BOPs)
  • Secondary Barrier Elements – BOPs (Ram Type Preventers) WL How to operate secondary barrier elements (braided line/electric line BOPs)
  • Shearing Devices WL Wireline shearing devices
  • PRESSURE CONTROL (BARRIER ELEMENTS and ENVELOPES) PRINCIPLES WL Grouping barrier elements into barrier envelopes during wireline operations
  • Other operations - PCE Stack WL The PCE rig-up during wireline fishing operations
  • Safely repair or replace a failed primary barrier element WL Secondary barrier elements and envelopes for slickline operations if a primary barrier element fails
  • Safely repair or replace a failed primary barrier element WL Secondary barrier elements and envelopes for braided line/electric line operations if a primary barrier element fails
  • PCE Rig Up WL The equipment required for a safe and compatible wireline PCE rig-up
  • PCE Testing WL The specific requirements for pressure testing/function testing PCE including wireline BOPs, shear/seal BOPs and valves
  • PCE Testing WL Testing the BOP with test rods
  • Operational Considerations (with well control consequences) WL The reason for wireline drift runs
  • Operational Considerations (with well control consequences) WL Surface Controlled Sub Surface Safety Valve (SCSSSV) integrity during a wireline operation
  • Operational Considerations (with well control consequences) WL Use and limitations of wireline cutter bars
  • Controlled Well Shut in WL Tool string positioning across the wireline BOP
  • Operational Considerations (with well control consequences) WL Force created by well pressure, flow and conditions compared to tool string/cable weight
  • Controlled Well Shut in WL Tool string positioning across the wireline BOP
  • Controlled Well Shut in WL Operating a wireline BOP
  • Controlled Well Shut in WL How to shut in the well quickly and safely with or without wireline in the hole
  • Loss of Pressure Control During Well Intervention Operations WL What to do if there are defects that could affect BOP function during a wireline operation
  • Loss of Pressure Control During Well Intervention Operations WL What to do if there is a failure in one component of the PCE during a slickline operation
  • Loss of Pressure Control During Well Intervention Operations WL What to do if there is a failure in one component of the PCE during a braided line/electric line operation
  • Loss of Pressure Control During Well Intervention Operations WL What to do if the wire is damaged during a wireline operation
  • Loss of Pressure Control During Well Intervention Operations WL What to do if there is a hydraulic control line leak on the Xmas Tree hydraulic master valve during a wireline operation
  • Loss of Pressure Control During Well Intervention Operations WL What to do if the hydraulic control line of the Surface Controlled Sub Surface Safety Valve (SCSSSV) leaks during a wireline operation
  • Loss of Pressure Control During Well Intervention Operations WL What to do if the BOP hydraulic control unit or hoses fail during a wireline operation
  • Loss of Pressure Control During Well Intervention Operations WL What to do if the wire breaks and falls downhole during a wireline operation
  • Loss of Pressure Control During Well Intervention Operations WL What to do if an alarm sounds when wireline is in the well and you are required to muster in a safe area

Refund policy